Project start: 2013
Project Completion: 2015
CLIENT INFO
Client: QATAR GAS
SERVICES PROVIDED
Energy and Utility
PROJECT DETAILS
Rerouting of existing fire water test line and provision of additional supports as needed based on the proposed modification and stress analysis to arrest
vibration.
• Hydraulic & Surge Analysis will be performed to resolve the presence of surge pressure in the fire water test line & to ensure the minimum pressure
drop within the test line.
• Installation of Anti cavitation type Pressure regulating valve to automatically relieve the excess pressure and to maintain constant system pressure at fire water pump test line.
• Installation of Restriction orifice to provide discrete pressure drop in order to minimize aquatics resonances and create suitable back pressure on the Pressure Regulating valve to prevent cavitation damage.